Building Owner
|
The Hong Kong & China Gas Company Limited
|
Using high volume low pressure (HVLP) ceiling fan for ventilated cooling
Using electronically commutated (EC) plug fan in AHU / PAU / CRAC
Replacement of high efficacy lighting source
Modernisation of lifts and escalators
| Building/Project Name |
Towngas Headquarters Building
| Systems |
HVAC - Airside Air Conditioning System HVAC - Carpark Mechanical Ventilation System Electrical System - Lighting Electrical System - Lift and Escalator
| Building Types |
Commercial - Office
|
Description of the building:
- Office in Industrial-Office Building with 28 floors (13 floors of offices, 5 floors of warehouse, 5 floors of carpark, 2 floors of multifunctional areas (11/F &12/F), B/F, G/F Entrance and R/F Plant Rooms).
- Fully air-conditioned with water cooled centrifugal oil free type VSD chillers, VSD Chilled Water Pumps and Cooling Towers.
- Air Handling Units and Fan Coil Units with pre-treated fresh air.
- ACVVVF Lift Control for Cargo Lifts.
- T5 LED Light Tubes.
|
|
 |
Retrofitted initiative:
HVAC-Air-side:
HVAC Primary Fresh Air System:
- Replacement of belt-driven centrifugal VSD fan in AHU/PAU by electronically commutated (EC) plug fan.
- Installation of High Volume Low Speed Ceiling Fans for 1/F Carpark.
Electrical Systems:
Lighting
- Replacement of all 13/F-25/F office lightings into T5 LED tubes.
Lift
- Cargo Lift Modernization of the existing DC Lift Control to ACVVVF Lift Control.
Observed benefits other than energy saving:
- Fan speed reduced and less noise created. Improved indoor air quality and nil complaint for insufficient fresh air.
- Produced a large scale of natural wind, ventilate and cool the air in large space.
- Reduced the maintenance cost and manpower cost by prolonged lifetime of the LED tube up to average 30,000 hours.
- Improved the operation stability and reliability, and reduced breakdown rate.
General observations of the retrofitting project:
- Fresh air supply system retrofit did not affect the users in general.
- The installation of 2 nos. HVLS fans in 1/F Carpark required extra personnel to conduct traffic control, in order to enhance site safety.
- Lightings were replaced in non-office working hours with sufficient advance coordination with users and cordoned-off the working area.
- Lift modernization required advance planning of lift arrangement, in order to minimizie the lift waiting time and the disturbance to the passengers.
Other information:
EC Fan |
|
Lift Modenisation |
 |
|
_350.jpg) |
|
_350.jpg) |
|
|
|
LED Lighting |
|
HVLS Fan in Carpark |
_350.jpg) |
|
 |
Cost |
Saving |
Total cost: |
HKD 9,224,000 |
Total savings/year: |
HKD 594,000 |
Cost breakdown: |
EC plug fan replacement for B/F AHU: HKD 30,000
EC plug fan replacement for G/F AHU: HKD 50,000
EC plug fan replacement for 21/F PAU: HKD 58,000
HVLS fans for 1/F Carpark: HKD 277,000
Replacement of LED tubes at 13/F-25/F: HKD 1,946,000
Cargo lift modernization: HKD 6,710,000
CRAC units with EC fans: HKD 153,000 |
Saving/year breakdown: |
EC plug fan replacement for B/F AHU: HKD 29,500 Payback: 1 year
EC plug fan replacement for G/F AHU: HKD 8,200 Payback: 6.1 years
EC plug fan replacement for 21/F PAU: HKD 6,000 Payback: 9.5 years
HVLS fans for 1/F Carpark: 7.4 years
LED tubes replacement: HKD 225,200 Payback: 8.6 years
Cargo lift modernization: HKD 261,100 Payback: 25.7 years
CRAC units with EC fans: HKD 26,900 Payback: 5.7 years
|
Payback: |
15.5 years |
|
|
Using high volume low pressure (HVLP) ceiling fan for ventilated cooling
Using electronically commutated (EC) plug fan in AHU / PAU / CRAC
Replacement of high efficacy lighting source
Modernisation of lifts and escalators
|
|
Building Owner
|
The Hong Kong & China Gas Company Limited
| Building/Project Name |
Towngas Headquarters Building
|
Systems |
HVAC - Airside Air Conditioning System HVAC - Carpark Mechanical Ventilation System Electrical System - Lighting Electrical System - Lift and Escalator
|
Building Types |
Commercial - Office
|
Description of the building:
|
- Office in Industrial-Office Building with 28 floors (13 floors of offices, 5 floors of warehouse, 5 floors of carpark, 2 floors of multifunctional areas (11/F &12/F), B/F, G/F Entrance and R/F Plant Rooms).
- Fully air-conditioned with water cooled centrifugal oil free type VSD chillers, VSD Chilled Water Pumps and Cooling Towers.
- Air Handling Units and Fan Coil Units with pre-treated fresh air.
- ACVVVF Lift Control for Cargo Lifts.
- T5 LED Light Tubes.
|
|
 |
Retrofitted initiative:
HVAC-Air-side:
HVAC Primary Fresh Air System:
- Replacement of belt-driven centrifugal VSD fan in AHU/PAU by electronically commutated (EC) plug fan.
- Installation of High Volume Low Speed Ceiling Fans for 1/F Carpark.
Electrical Systems:
Lighting
- Replacement of all 13/F-25/F office lightings into T5 LED tubes.
Lift
- Cargo Lift Modernization of the existing DC Lift Control to ACVVVF Lift Control.
Observed benefits other than energy saving:
- Fan speed reduced and less noise created. Improved indoor air quality and nil complaint for insufficient fresh air.
- Produced a large scale of natural wind, ventilate and cool the air in large space.
- Reduced the maintenance cost and manpower cost by prolonged lifetime of the LED tube up to average 30,000 hours.
- Improved the operation stability and reliability, and reduced breakdown rate.
General observations of the retrofitting project:
- Fresh air supply system retrofit did not affect the users in general.
- The installation of 2 nos. HVLS fans in 1/F Carpark required extra personnel to conduct traffic control, in order to enhance site safety.
- Lightings were replaced in non-office working hours with sufficient advance coordination with users and cordoned-off the working area.
- Lift modernization required advance planning of lift arrangement, in order to minimizie the lift waiting time and the disturbance to the passengers.
Other information:
EC Fan |
|
Lift Modenisation |
 |
|
_350.jpg) |
|
_350.jpg) |
|
|
|
LED Lighting |
|
HVLS Fan in Carpark |
_350.jpg) |
|
 |
Cost |
Saving |
Total cost: |
HKD 9,224,000 |
Total savings/year: |
HKD 594,000 |
Cost breakdown: |
EC plug fan replacement for B/F AHU: HKD 30,000
EC plug fan replacement for G/F AHU: HKD 50,000
EC plug fan replacement for 21/F PAU: HKD 58,000
HVLS fans for 1/F Carpark: HKD 277,000
Replacement of LED tubes at 13/F-25/F: HKD 1,946,000
Cargo lift modernization: HKD 6,710,000
CRAC units with EC fans: HKD 153,000 |
Saving/year breakdown: |
EC plug fan replacement for B/F AHU: HKD 29,500 Payback: 1 year
EC plug fan replacement for G/F AHU: HKD 8,200 Payback: 6.1 years
EC plug fan replacement for 21/F PAU: HKD 6,000 Payback: 9.5 years
HVLS fans for 1/F Carpark: 7.4 years
LED tubes replacement: HKD 225,200 Payback: 8.6 years
Cargo lift modernization: HKD 261,100 Payback: 25.7 years
CRAC units with EC fans: HKD 26,900 Payback: 5.7 years
|
Payback: |
15.5 years |
|
|
Using high volume low pressure (HVLP) ceiling fan for ventilated cooling
Using electronically commutated (EC) plug fan in AHU / PAU / CRAC
Replacement of high efficacy lighting source
Modernisation of lifts and escalators
|
|
|